The project includes demolition of the existing water standpipe and hydropneumatic tank, replacement of pumps, and installation of variable frequency drive (VFD) controls at the pump station. Additional work includes installation of a standby generator, switchgear, process piping, valves, flow measurement equipment, storage tanks, and associated mechanical systems. The project also includes electrical, instrumentation, and SCADA upgrades, structural and architectural improvements, concrete foundations, utility relocations, site grading, drainage improvements, fencing, gates, paving, demolition, startup and commissioning, and all associated civil, mechanical, structural, electrical, and site work necessary to provide a complete and reliable water system facility.